Restoration of Class 119 Driving Motor Brake Composite W51073

Ceiling
White Rabbits, White Ceiling

Progress reported on 04/06/13.

The white rabbits for a new month saw a push to complete the installation of the ceiling in the guards compartment. New white-faced hardboard was delivered in the week to allow this to happen. The sun was shining and it was one of those days where things just seem to go right and the team spent from 09:00 until 18:00 completing the task. It was quite a momentous occasion with the final panel being the final panel of the whole vehicle. The team have transformed the whole vehicle from a bare metal shell back into a usable vehicle.

The ceiling will be trimmed shortly and then glossed.

Sunday was spent with the sander preparing the doors for painting.

Left: A view of the completed ceiling.

Ceiling
Above: Another view of the completed ceiling
Repaint
Above: A progress photograph of the repaint. The lovely weather enabled the team to work outside.